Wilton Drive, Wilton Manors’ main thoroughfare is underwent an extensive construction and revitalization project. The new design improved traffic flow, widen pedestrian walkways and is in the process of adding new urban landscaping.
ROADWAY
STREETSCAPE
TIMELINE
One of the primary goals of the improvement project was to make Wilton Drive a safer and more pedestrian friendly boulevard. A lane elimination slowed down vehicle traffic while a dedicated bike lane and shorter crosswalks create a safer environment for our residents and guests. Click HERE to see the design plans for the roadway.
IMPROVEMENT PROJECT
OLD ROADWAY
IMPROVEMENT PROJECT
The second phase of the improvement project will be dedicated to the streetscape and landscape installations on Wilton Drive. Wider sidewalks and patio areas along with shady trees and lush landscaping will create a more enjoyable and comfortable pedestrian experience.
OLD SIDEWALK
IMPROVEMENT PROJECT
OLD SIDEWALK
IMPROVEMENT PROJECT
Click HERE to see the design plans for the roadway.
WHAT’S HAPPENING
Stage 1
September 2018
Roadway Project Begins
Stage 2
March 2019
Approval of Landscape & Streetscape
Stage 3
August 2019
Roadway Construction Completed
Stage 4
October 2019
Landscape/Streetscape Project Begins
Stage 5
October 2020
Landscape/Streetscape Project Completed